Frequently Asked Questions
The following FAQ's have been revised as of 7/13/2026. Archived FAQ's are located at the bottom of the page.
If you have questions that are not answered on this website or suggestions for FAQ additions, please send us an email at wildwoodprojectquestions@wpsk12.com
What is the Proposed Wildwood Project and its Current Status
Current FAQs (as of 7/13/26)
- What did the Wilmington Conservation Commission approve?
- Has the Order of Conditions been appealed?
- Can construction begin while the appeal is pending?
- What is a Licensed Site Professional, or LSP?
- Why was MassDEP not notified of the arsenic exceedances?
- How is arsenic determined to be naturally occurring?
- Is this a redevelopment or a new development project?
- What was the extent of soil testing on site?
- What environmental controls will be in place during construction?
- What happens if unexpected conditions are found?
- What about the monitoring wells on the property? Will the school be drinking from a groundwater source?
- What About the reported odor and the tannery claims? Is the project site a hazardous waste site?
- Could disturbed soils become an airborne health risk?
- Could disturbed soils become a groundwater risk?
- Are the off-site traffic improvements part of the Wilmington Elementary School Project, and how are they being funded?
- Why were the off-site traffic improvements discussed at School Building Committee meetings, and why are some people connecting them to the school project?
- Which intersections are being evaluated?
- Were these off-site improvements created only because of the school project?
What did the Wilmington Conservation Commission approve?
Has the Order of Conditions been appealed?
Can construction begin while the appeal is pending?
What is a Licensed Site Professional, or LSP?
Why was MassDEP not notified of the arsenic exceedances?
How is arsenic determined to be naturally occurring?
Is this a redevelopment or a new development project?
What was the extent of soil testing on site?
What environmental controls will be in place during construction?
What happens if unexpected conditions are found?
What about the monitoring wells on the property? Will the school be drinking from a groundwater source?
What About the reported odor and the tannery claims? Is the project site a hazardous waste site?
Could disturbed soils become an airborne health risk?
Could disturbed soils become a groundwater risk?
Are the off-site traffic improvements part of the Wilmington Elementary School Project, and how are they being funded?
Why were the off-site traffic improvements discussed at School Building Committee meetings, and why are some people connecting them to the school project?
Which intersections are being evaluated?
Were these off-site improvements created only because of the school project?
FAQ's (as of 8/18/2025)
- In the Town's cost estimation/projected tax impact, how much, if any of the project would be paid out of free cash or capital stabilization?
- What is included in the total project budget of $173.3 million for the PK–5 new construction project at the North Intermediate site?
- I was told that the MSBA is participating in roughly 55% of the Project costs. However, I was informed that there are ineligible costs beyond 55% of the Project costs. Can you please explain how the MSBA assesses reimbursement on a Project?
- Did the School Building Committee Conduct Public Forums and Obtain Community Engagement?
- Why is there discussion about having a full-sized gym (a.k.a. “high school-sized gym”) as part of the project? Is this necessary for school consolidation?
- Both new construction and addition-renovation options were studied at the North Intermediate site, why was the new construction option chosen?
- Is building the new consolidated PK–5 school at the North Intermediate site more expensive than other options?
- What are the Town's plans for the unused land if we consolidate multiple schools?
- Why not just repair the existing schools?
- Was a traffic analysis performed, and if so, what were the results?
- Another project in town will also affect traffic, the Amazon’s Sub-Same Day Delivery Operation at 800 Salem Street, what will be done to mitigate those traffic impacts?
- What would happen if the project were to fail?
- If the project were to fail, what would happen to the three elementary schools on the north side of Town from a facility standpoint?
- If the project vote were to fail in Town Meeting or at the ballot, what would happen to the delivery of education in Wilmington for our youngest learners?
- If the Wildwood Project passes, would the pathway of grades be replicated on the West Side of the Town?
- What sustainability elements are being incorporated into the design?
- Why is the project not planning to install solar panels?
- Why is the project not planning to install a geothermal heating and cooling system?
- Will the project meet all the necessary environmental and safety regulations?
- Have groundwater and runoff studies been done?
- Was the Wildwood Project presented to the neighborhoods at the North Intermediate location?
- Is there a plan for the existing pedestrian access from Arlene Avenue?
- What type of exterior lighting is planned for the new school, and how will it address safety, security, and impacts on the surrounding neighborhood?
In the Town's cost estimation/projected tax impact, how much, if any of the project would be paid out of free cash or capital stabilization?
What is included in the total project budget of $173.3 million for the PK–5 new construction project at the North Intermediate site?
I was told that the MSBA is participating in roughly 55% of the Project costs. However, I was informed that there are ineligible costs beyond 55% of the Project costs. Can you please explain how the MSBA assesses reimbursement on a Project?
Did the School Building Committee Conduct Public Forums and Obtain Community Engagement?
Why is there discussion about having a full-sized gym (a.k.a. “high school-sized gym”) as part of the project? Is this necessary for school consolidation?
Both new construction and addition-renovation options were studied at the North Intermediate site, why was the new construction option chosen?
Is building the new consolidated PK–5 school at the North Intermediate site more expensive than other options?
What are the Town's plans for the unused land if we consolidate multiple schools?
Why not just repair the existing schools?
Was a traffic analysis performed, and if so, what were the results?
Another project in town will also affect traffic, the Amazon’s Sub-Same Day Delivery Operation at 800 Salem Street, what will be done to mitigate those traffic impacts?
What would happen if the project were to fail?
If the project were to fail, what would happen to the three elementary schools on the north side of Town from a facility standpoint?
If the project vote were to fail in Town Meeting or at the ballot, what would happen to the delivery of education in Wilmington for our youngest learners?
If the Wildwood Project passes, would the pathway of grades be replicated on the West Side of the Town?
What sustainability elements are being incorporated into the design?
Why is the project not planning to install solar panels?
Why is the project not planning to install a geothermal heating and cooling system?
Will the project meet all the necessary environmental and safety regulations?
Have groundwater and runoff studies been done?
Was the Wildwood Project presented to the neighborhoods at the North Intermediate location?
Is there a plan for the existing pedestrian access from Arlene Avenue?
What type of exterior lighting is planned for the new school, and how will it address safety, security, and impacts on the surrounding neighborhood?
Archived FAQ's (to reflect updates above)
- Has there been any formal land analysis done on all three sites?
- Is parking and traffic being studied?
- What is the environmental impact of this project?
- What does each option do to the town budget and property taxes?
- If we must renovate/build multiple schools what does the total costs look like in the long term and what time period are we looking at?
- Does choosing one option over another impact other town projects? If so, which ones and how long does it defer the other projects?
- What is the status of existing debt - when does the debt from some prior larger projects (e.g. middle school/HS) start to roll off the budget?
- If the Prek-K option is chosen, what is the plan for the North Intermediate School? Will there be upgrades made?
- What is the cost to the Town to add an additional 6000 sf to the gymnasium, making it high school sized?
- Is the Wildwood School Building Committee responsible for determining what happens for school building/renovation projects for the schools on the West side of Town? (i.e., Boutwell, Shawsheen, and West Intermediate)?
- What is the realistic scenario that the Town can get another MSBA grant as soon as this project is done knowing that we already received the grant twice recently when some communities never get it?
- Will the residents be asked to support the project as part of a Special Town Meeting or as part of the Annual Town Meeting? When will this Town Meeting be held?
Has there been any formal land analysis done on all three sites?
Is parking and traffic being studied?
What is the environmental impact of this project?
What does each option do to the town budget and property taxes?
If we must renovate/build multiple schools what does the total costs look like in the long term and what time period are we looking at?
Does choosing one option over another impact other town projects? If so, which ones and how long does it defer the other projects?
What is the status of existing debt - when does the debt from some prior larger projects (e.g. middle school/HS) start to roll off the budget?
If the Prek-K option is chosen, what is the plan for the North Intermediate School? Will there be upgrades made?
What is the cost to the Town to add an additional 6000 sf to the gymnasium, making it high school sized?
Is the Wildwood School Building Committee responsible for determining what happens for school building/renovation projects for the schools on the West side of Town? (i.e., Boutwell, Shawsheen, and West Intermediate)?
What is the realistic scenario that the Town can get another MSBA grant as soon as this project is done knowing that we already received the grant twice recently when some communities never get it?
Will the residents be asked to support the project as part of a Special Town Meeting or as part of the Annual Town Meeting? When will this Town Meeting be held?
Additional Community Questions
Details coming soon